Short answer
Light foot traffic: 30–45 minutes after application.
Set / hardened: 1 day after application.
Start the clock
Your countdown
Stated times
- Light foot traffic30–45 minutes
- Set / hardened1 day
From DAP data sheet · checked 2026-10-24. Anything not listed isn’t stated by the manufacturer.
Conditions & fine print
- Stated conditions: Not stated in the data sheet
- The data sheet lists two minimum temperatures (40°F and 45°F), so this site shows no range. Do not use if rain is likely. Fill deep cracks in 1/4 in. layers, 24 hours apart.
- Region US. Formulas can differ between countries; check your container.
- Entered from the manufacturer source; second review pending. Report outdated information
- Actual results depend on preparation, thickness, ventilation, temperature, humidity, mixing and substrate.
Questions
How long before Liquid Cement Crack Filler is light foot traffic?
DAP states: Repairs are ready for traffic 30–45 minutes after application. This is the manufacturer’s stated time, not a guarantee.
How long before Liquid Cement Crack Filler is set / hardened?
DAP states: Set time: 24 hours. This is the manufacturer’s stated time, not a guarantee.