How long before flooring can be installed over it?

Use the milestone for flooring installation, not a generic dry-to-touch time. The table below is built only from numeric times in manufacturer documents already recorded in our catalog.

Important: Shortest does not mean interchangeable. Product type, surface, conditions and intended use still have to match your project.

Manufacturer-stated times

ProductManufacturer-stated minimumCondition/source
MAPEI Planiprep SC
Cement-based smoothing compound
30 minutesDepends on thickness and environmental conditions.
Sika Level-325 Self-Leveling Underlayment
Powder (all sizes)
4 hoursAbove 3/8 inch, the data sheet calls for a mat test (ASTM D-4263).
Custom Building Products SpeedSlope Rapid Setting Sloping Mortar
Powder (all sizes)
6 hoursSome flooring finishes may need longer to reach lower moisture levels.
ARDEX K 15 Premium Self-Leveling Underlayment
Powder (all sizes)
16 hoursAt 70°F (21°C).
Custom Building Products LevelQuik RS Rapid Setting Self-Leveling Underlayment
Powder (all sizes)
16 hoursThe data sheet gives no conditions for this time.
LATICRETE NXT Level Self-Leveling Underlayment
Powder (Spanish-language data sheet)
16 hoursGood drying conditions: air at 65 to 75°F (18 to 24°C) and 40 to 60% relative humidity.
Henry 544 Floor Leveler
Powder (all sizes)
1 daysAt 70°F (21°C).
LATICRETE NXT Level Flow Self-Leveling Underlayment
Powder (Spanish-language data sheet)
1 daysGood drying conditions: air at 65 to 75°F (18 to 24°C) and 40 to 60% relative humidity.

How to use this table

Open the exact product page to see the variant, source wording, stated conditions and other milestones. A minimum time is the earliest stated threshold under the manufacturer’s conditions—not a guarantee for colder, wetter, thicker or poorly ventilated applications.

Related checks

  • Confirm the exact formula and region on your container.
  • Use the clock for your next action rather than touch-dry time.
  • Check temperature, humidity, thickness and substrate notes.
  • When the manufacturer provides no correction factor, wait longer and verify physical readiness.